When the scan says "not installed," and the trade says "we did it," the answer might be a quality problem, not a data error
▶ WATCH THE FULL PRESENTATION
Computer Vision Is the Andon Cord Construction Has Always Needed
LCI Conference 2025 · Reid Senescu, Doxel & Mike Miller, DPR Construction
Doxel's system was designed to track progress, but on a hyperscale data center project with DPR Construction, it caught something that no daily report, RFI, or schedule update had flagged, and the lesson that came out of it changed how the team interpreted data discrepancies entirely.
The story starts with a flag. Doxel's AI detected uninstalled security components near certain doors. The electrical trade partner pushed back hard, claiming they had roughed in all the security to those doors. In their estimation, the work was done.
After further investigation, the team found the truth: the security boxes had been installed. Three feet to the right of where they were supposed to be.

The components had been physically installed, but they were mislocated relative to the BIM. When comparing the 360° site photos against the model, Doxel’s AI correctly identified them as not installed in the designated location.
"If something's showing as not installed and the trade partner says it's installed, we probably have a quality control problem. Not the intended use case — but awesome to see."
— Mike Miller, Superintendent, DPR Construction
The team had stumbled onto a new interpretive principle. When Doxel flags something as missing and the trade says it's done, don't default to assuming the data is wrong. Investigate. The discrepancy might not be a tracking error; it might be a quality flag.
Mike was direct about what happened next and what it cost. Rework followed. But by investigating when they did, the team headed off even higher costs than if the issue had been found later.
REWORK WARNING: Dismissing data because it contradicts expectation is how quality issues get buried. The cost of investigation is almost always lower than the cost of rework — especially once walls are closed.
This is not an abstract lean principle. It played out on a real job, on real infrastructure, with real rework costs. The lesson is practical: when scan data and field reports disagree, treat the disagreement as information, not noise.
Construction quality management has traditionally relied on scheduled inspections, trade self-reporting, and periodic walkthroughs. These methods work reasonably well for obvious defects. They are poor at catching components that are physically present, but are installed in the wrong place relative to the design.
Computer vision can fill this gap by comparing what is physically present against the BIM at the component level across all visible trades every week. Mislocations look identical to missing components from the system's perspective, because in both cases, the component is not where it should be.
The practical recommendation from Mike's experience is to establish a protocol for investigating discrepancies rather than defaulting to dismissal. When a trade reports complete and the system reports incomplete, send someone to review the discrepancy. It only takes minutes, but it can prevent weeks of rework.
There is a secondary benefit this story highlights: objective, time-stamped documentation of installation location for every component. On a complex facility like a data center, where systems are dense, and modifications may be needed years later, having a record of where things were actually installed, not just where they were designed to go, has ongoing operational value.
This use case wasn't in the sales deck. It emerged from a real disagreement on a real job. That's often how the most durable capabilities get discovered.

Doxel is proving that transforming an industry starts with the people behind it.
Doxel has been recognized by Forbes as one of America’s Best Startup Employers, highlighting the company’s rapid growth, strong culture, and commitment to developing talent in construction technology.

The annual Forbes ranking evaluates thousands of startup companies across the United States based on employer reputation, employee satisfaction, and growth. The recognition reflects the impact Doxel has built not only in transforming construction productivity but also in creating a workplace where employees can build meaningful careers.
You can see the full list here.
Doxel develops AI-powered construction progress tracking technology that helps owners and contractors deliver projects faster and with greater certainty. By automatically capturing jobsite data and comparing it to BIM models and project schedules, the platform provides objective visibility into construction progress and productivity.
The system helps teams eliminate manual reporting, gain objective insights, and make faster decisions across complex construction projects.
For Saurabh Ladha, CEO and Founder of Doxel, the Forbes recognition reflects years of commitment to both innovation and people.
“Our mission has always been to transform how the world builds. That requires not only great technology, but great people. Being recognized by Forbes as one of America’s Best Startup Employers is a testament to the incredible team we have built at Doxel.” - Saurabh Ladha, CEO and Founder of Doxel
Ladha added that solving construction’s productivity challenges requires long-term thinking and strong collaboration across engineering, product, and customer success teams.

Employee satisfaction has played a major role in Doxel’s recognition.
The company currently maintains a Glassdoor rating of approximately 4.1 out of 5, reflecting strong employee feedback on leadership, culture, and career opportunities.
Many employees highlight the opportunity to grow quickly within the organization and take on new responsibilities as the company scales.
“If you’re looking for a fast-growing company that genuinely supports career progression, values its people, and maintains a strong culture as it scales, Doxel is a great place to be,” said one account team member.
Another employee noted that Doxel’s leadership actively supports internal promotions and professional development.
“The career advancement opportunity has been great! I've been given several opportunities to be promoted to higher leadership roles over the past few years.”
Construction remains one of the world’s largest industries, yet productivity has stagnated for decades. According to research from McKinsey, construction productivity grew only 0.4% annually between 2000 and 2022, far behind gains in manufacturing and the broader economy.
Doxel’s technology addresses this challenge by providing automated, objective progress tracking across construction sites. The platform scans projects, compares actual progress against plans, and helps teams identify schedule risks earlier.
Companies using Doxel gain:
These insights allow project teams to make faster decisions and keep complex projects on track.
For Doxel employees across engineering, AI research, and customer success, the opportunity to solve real problems in construction has become a major motivator.
“We’re not just building software,” said Reid Senescu, Sr. Vice President of Product, Marketing, and Customer Success. “We’re helping an industry that builds hospitals, data centers, and infrastructure deliver projects faster and with more certainty.”
That mission has helped Doxel attract talent from both technology and construction backgrounds, creating a team with deep expertise across AI, robotics, and capital project delivery.
The Forbes recognition highlights Doxel’s momentum as the company continues expanding its technology platform and customer base across major global construction projects.
For Ladha, the award reflects the culture the company intends to preserve as it grows.
“Our goal is to build a company where talented people can do the best work of their careers while solving meaningful challenges for the construction industry.”
- Saurabh Ladha, CEO and Founder of Doxel


How AI progress tracking gives superintendents a signal weeks before a delay becomes a crisis
LCI Conference 2025 · Reid Senescu, Doxel & Mike Miller, DPR Construction
Every superintendent knows the feeling: a trade partner reports they're on track, the schedule says green, and then, one week before a milestone, the reality hits. The work isn't there. The cascade starts. The conversations get harder.
The problem isn't that anyone is lying. The problem is that construction progress has always been measured the same way: someone walks around, someone asks, someone estimates. By the time a deviation surfaces through normal reporting channels, weeks have passed, and the cost of recovering has multiplied.
Data-driven construction executives are disciplined in leveraging technology and processes to capture crucial information about their projects. At LCI Conference 2025, DPR Project Executive Mike Miller described how automated progress tracking changed that dynamic on his hyperscale data center project, starting with a piping trade partner whose slip he could see forming in real time.
Starting in December, Doxel's computer vision system began showing a divergence between the piping trade's actual installed quantities and their planned schedule. Not a dramatic gap at first. Just a signal.
Under traditional reporting, that gap might not have surfaced until a formal schedule update meeting or until it cascaded into delayed downstream trades. With automated tracking, Mike could see it forming week by week, grounded in automated progress tracking rather than self-reporting.
"As a leader, you only have so much time to focus on certain things. I can't focus on everything all the time. I can see who's on plan and I can focus where we have the risk."— Mike Miller, Project Executive, DPR Construction
What followed was a textbook plan-do-check-act (PDCA) loop. The trade was brought to the table. The data was shared. Initially, there was resistance — new tools, new data, trust takes time. But by year-end, the team accepted the picture and decided to add resources. Check the result. Adjust again if needed.
Mike called it "bread and butter." The system is working exactly as it should.

KEY INSIGHT Early detection gives leadership the visibility to have the right conversation at the right time.
The lean parallel is direct. In manufacturing, the Andon cord's value isn't the cord itself; it's the organizational culture that responds to it. Doxel's computer vision functions as a continuous Andon cord across the entire job site, flagging deviations the moment they're detectable, not weeks later when they've compounded.
Reid Senescu, Head of Product at Doxel, described the underlying principle: construction sites have historically lacked the sensor layer that lean manufacturing has always relied on. No factory would operate without real-time feedback on production output. Yet construction, which is far more complex and expensive, has run primarily on estimates and walking the site.
The system takes three inputs:
Computer vision compares the scan against the BIM to determine what has been physically installed at the component level across all trades and at every stage of construction. A large language model ties the schedule to the BIM, producing a real-time 4D view of the actual project state versus the planned state.
The result: trade and project-level progress data grounded in physical observation rather than self-reporting, updated at least weekly, with no additional engineering work required for onboarding.
Doxel has captured over 3 billion square feet of construction. That dataset powers the "rules of credit" — weighted effort models that let the system aggregate component-level data up to an accurate project percent complete.
What This Means for Owners and GCs
For owners, the implication of this story is straightforward: the capability exists to monitor capital investments in construction with the same rigor applied to financial data, inventory, or operational metrics. Requiring automated progress tracking in the RFP: specifying that it must cover all visible trades and at least 80 stages of construction is the most direct way to ensure this capability is on every project.
For GCs like DPR, the story is about competitive differentiation. The teams that build trust in objective data and act on it early catch problems before they cascade. They spend less on rework and recover faster.
The Andon cord is finally available for job sites. The question is how quickly the team can respond when it sounds.
With automated tracking, construction teams can ensure that 'almost done' quickly becomes 'completely done.
Let’s face it: Getting stuff done is hard. And getting stuff done in the face of today’s shortages, supply chain issues, and inflation is a daunting task for any construction company. Automated construction progress tracking can help you finish projects faster.
Before we get into that, let’s take a closer look at what’s going on.
Less people from younger generations are choosing a trade or apprenticeship. As a result, the industry is facing a shortage of skilled workers to help complete project milestones. Without knowing how many people can get the work done (and get it done correctly), companies struggle to stay on track.
Those who do choose to go into construction today are still green in their careers and don’t have the experience that seasoned employees do. This creates a learning curve and requires additional time needed to get them up to speed.
Unpredictable factors create unpredictable change—and change requires an added degree of flexibility for the project to adapt to the circumstances. As a result, companies are seeing more design changes come through, and the need to stay on top of assessing and documenting them.
Speaking of unpredictable, the industry ha seen an influx in supply chain issues, causing delays in shipments and—in some cases—a limited supply of the necessary materials available.
Across every industry, prices are going up. Companies must now reconcile their bids and project scopes to maintain profitability.
When the going gets tough, construction stays tougher. The industry is no stranger to uncertainty. Now more than ever, companies need to pinpoint areas of improvement and streamline their processes to maximize efficiency.
With all these factors weighing on a project’s productivity, the margin for error is very low—which means operational excellence is critical for success. Many projects get to a certain stage or near completion, but struggle to accurate assess what’s happening (or not) to get the rest of the way there.
Almost done isn’t done.
If the last 10% of a milestone takes more than 20% of the time—that’s a big, potentially costly, problem.
That’s where automated construction progress tracking comes in. With the right technology in place, companies can save 25% of superintendents’ and field teams time that would otherwise be spent on tracking progress and bringing everyone on the same page. That’s less time in meetings and back-and-forth conversations, more time building.
Real-time automated construction progress tracking gives everyone on a project visibility into the current state, without the need for individual communication. This ensures the project moves as quickly as it can and prevents trade stacking.
Stay on top of milestones with the ability to forecast and predict any slowdowns before they happen—instead of catching them after it’s too late. By automatically capturing more than 75 stages of construction, automated construction progress tracking technology can spot potential issues more efficiently in real time.
By providing accurate and automated cost budget analysis, companies are able to better understand their project and where it stands with the budget. When unforeseen factors or delays hit, you want all the knowledge and numbers you can get to properly adapt and minimize the impact.
In construction, communication can be slow and sparse. Automated construction progress tracking gets everyone on the same page without having to meet to discuss. Having a digital surveyor gives everyone the information and insights they need to collaborate faster—without relying on project resources to collect and report on it.
No matter what gets thrown at the construction industry, a company needs to be resilient and smart to see success on the other side. Companies who invest in the right tools that save time and automate processes have the advantage of receiving data and insights in real time. The faster something is flagged, the faster it can be fixed.
Want to learn how Scripps Health and McCarthy Building Companies are automating construction progress tracking to increase project visibility? Register for our upcoming webinar Almost Done, Isn’t Done.
Streamlining the process for creating detailed reports can free up the project team's focus while enhancing the level of reporting and insights for a company.
In a 2021 Workforce Survey Analysis, AGC found that 88% of companies surveyed were experiencing project delays—that’s nearly nine out of ten. Now more than ever, construction companies are faced with the challenge to do more with less and keep projects on track in the face of unforeseen circumstances.
While certain conditions and factors in the industry can’t be controlled, there are 3 construction workflows that can reduce the margin of error to ensure a project stays resilient. This requires operational excellence in the areas that can be predicted and made more efficient.
What are the three construction workflows a company should prioritize?
Communication among field teams, supervisors, and the office is crucial—and can be cumbersome. With so many moving pieces of a project happening at once, getting the necessary message out to everyone in a timely, effective manner is no easy feat.
Companies need to find a way to remove the barriers to communication. By doing so, they’ll save everyone on the project team valuable time that would otherwise be spent tracking progress, in meetings to get everyone up to speed, or playing telephone.
Quality of construction can make or break a project’s ability to stay on track. Quality issues or mistakes found too late in the process can be the kiss of death for moving onto the next phase—and as a result, teams remain stuck in the final 10 or 20% of completion for too long. This won’t just cost time and manpower, it’ll directly affect a project’s budget and profitability, too.
The only option to streamline and prevent these costly quality issues is to catch them early and address them quickly. Technology that helps companies see progress in real time opens the door for making smarter decisions and adapting faster.
When a project does make it through the final 10%, the work isn’t over yet. Teams must provide an objective, detailed overview of the completion—which again takes time and resources. There’s more information to gather, and no efficient way to compile it using manual efforts alone.
Teams should be focused on projects, not paperwork or reporting. Streamlining the process for creating detailed reports can free up their focus while enhancing the level of reporting and insights for a company.
By implementing a technology that can continuously monitor performance and provide predictive insights, construction companies are able to achieve operational excellence.
Platforms like Doxel act as a digital surveyor to automatically track progress across more than 75 different construction stages in real time, freeing up the project team’s time and resources.
Instead of manually walking the jobsite every day or week to capture exact progress, Doxel works with a 360° video to act as a digital surveyor in minutes. Combining the power of computer vision with BIM means companies have an objective truth of the status of a site—and can understand progress, schedule, and budget better than ever before.
If it sounds too good to be true, it isn’t.
Tune in to our webinar Almost Done, Isn’t Done to hear from two successful construction companies on how they’re leveraging real-time progress tracking to automate and achieve more.
By continuously tracking and analyzing construction site progress in real time, Production Rate Data serves as a single, reliable source of truth for measuring construction progress.
Traditionally, project managers have relied on site visits and progress reporting from their field teams to stay abreast of construction progress. On large capital projects like data centers, semiconductor wafer fabrication plants, or healthcare infrastructure this can become problematic where even small schedule delays lead to large cost overruns. Doxel’s Production Rate Data provides a solution that empowers project teams with additional data in order to monitor construction progress.

Production Rate Data is the information gathered through reality capture inputs (e.g., 360-degree imaging or drone footage), to continuously track and analyze construction site progress in real time. By comparing actual work completed against the planned schedule, this data serves as a single, reliable source of truth for measuring construction progress. It provides project owners with objective, accurate insights that are crucial for managing schedules and ensuring on-time project completion. This innovative approach equips teams with the data needed to identify delays, optimize workflows, and ensure efficient project delivery.
By leveraging this advanced technology, owner’s representatives can monitor projects with a data set they control, guaranteeing transparency and accuracy. Here’s how Doxel tracks completed construction:
Example: Mechanical Pipes and Walls

Doxel’s Production Rate tracking capability simplifies the comparison of completed construction against the schedule, offering a powerful tool for project owners to measure progress and manage schedules effectively.
Understanding how construction software tracks progress can be complex. Doxel simplifies this with a robust methodology:

Productivity is calculated using specific units of measure for each stage based on your work breakdown structure (WBS) in Primavera P6. For example, if the plumbing installation requires 100,000 linear feet of pipe, the unit of measure would be linear feet. The planned number would be 100,000, against which completed construction is measured.
As construction progresses, Doxel updates the number of completed activities. For instance, if only 20,000 linear feet of pipe have been installed for the drainage system, the 360-degree imaging would capture the work, and Doxel would update the percentage of completion for both the stage (drainage system) and the trade (plumbing) to 20%.
To help manage schedules effectively, Doxel introduced the Production Forecasting Calculator. This tool allows users to simulate different scenarios by adjusting crew sizes and production rates to forecast completion. General contractors can manage subcontractors to ensure they stay on schedule. At the same time, owner’s reps can monitor production rates remotely, gaining confidence that construction progress is on track based on actual data.

Production Rate Data compares completed construction against your schedule, providing a single source of truth for measuring construction progress. Doxel’s system allows you to manage productivity for each stage of the construction project by trade, zone, and floor. This capability empowers project owners with a controlled data set that facilitates better communication with general contractors and helps address potential schedule delays proactively.
By giving project owners control of the data, Doxel ensures a higher level of transparency and efficiency in construction management. This innovative approach enhances collaboration and significantly reduces the risk of delays, optimizing time and resources. With Doxel’s Production Rate Data, project owners can confidently steer their projects to successful completion.
Accurate and reliable progress tracking is essential for effective communication and coordination, especially with multiple stakeholders and a higher level of complexity. Automated construction progress tracking can meet these requirements and reduce manual effort, helping you complete your projects faster and on-budget.
Healthcare construction is more complex and has a lot at stake. If not done right, these projects can be costly for everyone involved. Healthcare projects also require a higher attention to detail to keep everything running smoothly.
With more stakeholders involved in the process, companies need to be able to benchmark and be equipped for better prediction, transparency, and ultimately the ability to detect (and curb) problems, deviations, and cost overruns.
Automated progress tracking can meet these requirements and reduce manual effort, helping you complete your projects faster and on-budget.
Progress tracking is critical for project success in healthcare because it allows for real-time monitoring of project performance and a faster identification of issues and challenges, and implementation of corrective actions.
By regularly monitoring progress and performance, project managers and teams can quickly identify areas that are falling behind schedule or budget—and take the necessary steps to address them before they become major issues. Accurate and reliable progress tracking is essential for effective communication and coordination, especially with multiple stakeholders and a higher level of complexity.
Progress tracking can be beneficial beyond one single project, too. Objective progress data and insights can also help to identify areas of success and best practices that can be replicated in other projects, improving overall project performance and company-wide outcomes.
Automated progress tracking can improve transparency during hospital construction by providing real-time, accurate information on the progress of the project. Automated systems can be configured to collect data from a variety of sources, create a single source of truth and present the information in a format that is easy to understand and always accessible.
With the enhanced, real-time visibility that automated progress tracking brings, stakeholders are able to see exactly where the project is at any given time. This clear picture of project status helps improve communication, transparency, and accountability with objective data that eliminate any debate in progress tracking.
Automated progress tracking is a faster way of providing stakeholders with access to the same information. With an automated system, stakeholders are able to see the same data and reports, regardless of their location. Ensuring everyone is working with the same information saves time in reporting and mitigates the possibility of miscommunication or misunderstanding.
Since hospital construction projects often involve large sums of money and have a significant impact on patient outcomes, it’s also useful to have an auditable record of each project’s progress that can be used in demonstrating accountability to funders and regulatory bodies.
Healthcare construction projects need an efficient way to manage and mitigate risk. Proper real-time visibility into the progress of the project can help spot potential issues before they become major problems. This enables project managers and other stakeholders to take proactive measures, rather than waiting until it is too late to take corrective action.
For example, if progress tracking reveals a particular aspect of the project is running behind schedule, the project manager may be able to adjust the project plan to effectively avoid potential delays or cost overruns.
Additionally, progress tracking can help project managers manage and coordinate dependencies between different parts of the project, which further reduces the risk of delay, prevents trade stacking, and mitigates other issues arising from one part of the project impacting others.
Progress tracking can help with benchmarking by providing a clear understanding of the current status of the project, including the status of all trade and any related delays or setbacks. This data can then be used to compare the project’s progress against similar projects or industry standards, making it easier to identify areas where improvements can be made.
With multiple sources of information on a single project, a digital progress tracking tool can deliver accurate data to one shared source of truth, making benchmarking markedly easier.
Additionally, progress tracking stored data can be leveraged for benchmarking future progress against previous internal projects for better forecasting future project and completion dates, as well as for identifying potential cost savings or other opportunities to optimize the project.
The more detailed information teams have on the progress of a project, the more proactive they can be to keep it on track. Identifying potential issues early on allows for corrective action to be taken sooner rather than later, reducing hours, rework, and delays to deliver projects on time and on budget. But detailed and timely progress tracking shouldn’t come at the cost of crews’ time and resources.
That’s where a solution like Doxel’s automated progress tracking can help. Doxel significantly reduces hours tracking progress, while delivering accurate, reliable objective insights that improve communication and transparency across all stakeholders.
Click here to learn more about how Doxel’s AI-powered progress tracking paired with 360-degree video capture can help ensure hospital construction projects stay on track and on budget.
Healthcare construction teams that leverage AI-powered performance monitoring are armed with accurate data in near real-time to keep projects on track.
Healthcare construction is a specialized niche in the industry, and the projects within it require a high standard of attention to detail to meet their deadlines. These projects are complex and involve the coordination of large, cross-functional teams to complete them on tight schedules—which means a project’s success is majorly dependent on the efficiency and collaboration of the team building it.
Every day that the facility is delayed or past schedule means another day patients can’t come in, and the owner or company will lose money.
Enter, AI-powered project controls – automated construction progress tracking.
The construction of healthcare projects is a delicate balance of innovation and realism. As one of the more technology-driven sectors, these facilities aim to have the latest and greatest equipment, but at the same time needs to be planned months in advance and available within a certain deadline. Teams must stay on top of an ever-changing landscape and varying demands—so having accurate, objective project progress data throughout is essential.
One of the biggest factors to staying on schedule is knowing exactly where you are. Without a single view of project progress, sticking to a set schedule becomes a risky guessing game. Progress tracking using the power of computer vision enables project teams to build faster and more accurately together.
After all, knowledge is power. Teams that leverage AI-powered performance monitoring are armed with accurate data in near real time to see backwards at what’s been done, as well as ahead at predictive insights.
Rework can be a project schedule’s worst nightmare—and the later it’s caught the bigger a scheduling headache you have on your hands. Rework takes valuable time away from what should be forward progress. In order to achieve schedule predictability, a project team has to be able to spot (and avoid) potential rework on the critical path.
Using computer vision automated construction progress tracking that acts as a digital surveyor, superintendents can quickly catch any missing or incorrectly installed components before the next trade covers up the error. This foresight can help avoid weeks of delays and schedule compression, which ultimately helps the facility stay on track to open on time or earlier.
Real-time automated construction progress tracking doesn’t just help with new healthcare construction—it can also help reduce downtime during facility operations down the road.
Picture it (if you dare): A construction company closes off an area to cut into the wall and fix MEP services only to discover that it wasn’t installed per as-built plans. Instead of adhering to the plan, dreaded rework is now required.
But what if you had x-ray vision instead? Comprehensive reality capture of an as-built facility ensures maintenance teams know exactly what was installed and where, so any maintenance and retrofits can be done efficiently without the rework. Instead of costing days of downtime, teams can get in and get it done as planned the first time.
At its core, Doxel is automated construction progress tracking that provides objective, accurate data on materials installed for real-time project controls. The more teams can document in the moment, the more productive and proactive they become.
Find out how healthcare projects have used Doxel to deliver facilities earlier and at a higher standard of quality.
Doxel is thrilled to partner with Corscale in revolutionizing the landscape of data center construction, setting a new standard for the industry.
Gainesville, VA – (November, 2023) – Corscale, the exclusive data center platform of the Patrinely Group, has announced that it will be deploying Doxel, the leader in AI automated construction progress tracking to speed the pace of construction and reduce waste on upcoming data center construction.
“Corscale is focused on implementing industry leading construction and sustainability initiatives. We are committed to building efficiently. Doxel will help us accelerate construction schedules and deliver critical data centers faster.” said Nic Bustamante, Chief Technology Officer for Corscale. Prior to his current position, Nic was the Senior Vice President of Development at Corscale and held leadership roles at Apple, Google, and Microsoft.
The rise in artificial intelligence, specifically Natural Language Processing (NLP), computer vision, and machine learning, and robotics, is increasing the already strong demand for data center solutions. Corscale will now harness the power of AI to build the data centers that deliver AI.
“Doxel is thrilled to partner with Corscale in revolutionizing the landscape of data center construction. Corscale’s commitment to industry-leading initiatives aligns with Doxel’s mission to transform construction through the power of AI. We aim to enhance the efficiency and sustainability of constructing data centers, setting a new standard for the industry. This collaboration represents a significant stride toward the future, where AI not only powers data centers but also drives their seamless and sustainable construction.” – Saurabh Ladha, CEO of Doxel.
The partnership with Doxel reflects Corscale’s forward-thinking approach to stay at the forefront of technological advancements. By incorporating AI into the construction process, Corscale not only meets the rising demand for data center solutions but also pioneers a path toward intelligent, sustainable, and swift data center deployment.
Corscale Data Centers is focused on delivering sustainability at scale. As the exclusive data center platform of the Patrinely Group, Corscale, together with its capital partner USAA Real Estate is delivering tomorrow’s data center, today. The company has assembled a top-tier team of industry professionals who bring decades of experience designing, building, and operating sustainable, high-density data centers for some of the largest and most sophisticated hyperscale operators and enterprises. Corscale delivers highly scalable, secure, and energy-efficient build-to-suit powered shells as well as flexible modular deployments. To learn more, please visit Corscale.
Doxel is focused on speeding up construction and reducing waste by using AI to automate progress tracking. Doxel believes in the power of aligned teams and designed Doxel to unlock their full potential. With Doxel, owners have full observability on their site while providing their field teams with powerful tools that prevent delays, over-billing, re-work, and trade stacking. Backed by Insight Partners, Amplo, and Andreessen Horowitz and with a growing team of engineers, scientists and construction veterans, Doxel is driven to help their customers win.
For media inquiries, please contact:
Corscale Media Relations
press@doxel.ai
Doxel Media Relations
press@doxel.ai
Accurate, reliable data allows construction companies to remove subjectivity and replace it with objective accountability.
Communication can make or break a construction project. A report from the Project Management Institute found that ineffective communication was the main contributor to project failure one-third of the time. An even more alarming finding from the research is that 56% of budgets allocated to projects are at risk due to poor communication.
Without objective insights alignment among field and office teams, knowing what’s happening on a project becomes a daunting task—one that could put a project (and its profitability) at risk.
1. Delayed communication
Timely communication (especially between the field and the office) is hard to achieve. Field teams are focused on a hundred different things at once, and relaying project updates typically happens at the end of their day. Because field leaders aren’t able to instantly communicate every facet of a project’s progress as it happens, there is a lag time and gap in each day’s reporting.
2. Inconsistent communication
In addition to being delayed, communication from the field to the office isn’t always consistent. The more variables and people added to the equation, the more potential for confusion and uncertainty. Communication on a project can very quickly turn into a game of telephone—and teams are forced to hold more meetings and conversations to ensure mutual understanding.
3. Missing communication
While delayed and inconsistent communication can hold a project back, missing communication can halt it entirely. If proper communication isn’t happening, neither is profitable building.
All these challenges in communication don’t just create extra stress and work on a project—they can have a deeper impact on the data and tracking, too. Without everyone on the same page, the reporting and insights are left to everyone’s individual perspective. As a result, the project’s insights suffer.
Accurate, reliable data allows construction companies to remove subjectivity and replace it with objective accountability. Insights that are trackable and consistent bring everyone together on the same page to make informed decisions, faster.
Improve communication and progress tracking
Streamline billing and accountability
The key to collecting reliable insights is through automated progress tracking. The right tool can increase team alignment and communication, without adding effort to the project team’s plate.
Doxel brings predictability to construction projects by providing critical insight with objective analytics. The AI-powered computer vision builds a digital twin of the jobsite on a weekly basis—providing true progress reporting and near real-time data. Doxel acts as a digital surveyor to capture and quantify project progress and eliminates the need for teams to manually calculate and report on it. The result is detailed, shared progress tracking from a single source across every project stakeholder and subcontractor.
Strategies for maintaining a healthy work-life balance.
Doxel CEO Saurabh Ladha is featured on The QTS Experience Podcast with David McCall. David and Saurabh discuss the impact of waste and rework in construction.
Saurabh discusses how Doxel integrates AI with established processes to build faster. Join us for the conversation, on the next QTS Experience. Episode 191; Saurabh Ladha: Intuitive Construction, AI, Doxel, Innovation, Data Center.
Doxel is excited to be part of the conversation, joining top industry experts to discuss how better project execution and early visibility reduce change orders and accelerate speed to market. Visit us at Booth #37.
📅 March 17–19, 2025 | 📍 Salt Lake City, Utah
The Advancing Data Center Construction (ADCC) West conference is where data center leaders, contractors, and technology providers come together to address the most pressing challenges in mission-critical construction. This highly focused event delivers actionable strategies, industry insights, and opportunities to engage with key decision-makers in the field.
Doxel is excited to be part of the conversation, joining top industry experts to discuss how better project execution and early visibility reduce change orders and accelerate speed to market. Visit us at Booth #37.
ADCC West is designed specifically for mission-critical construction teams, covering topics such as supply chain constraints, scheduling challenges, and client-driven expectations. The conference’s new dual-track format allows attendees to focus on emerging industry trends or practical solutions to improve project delivery.
The industry’s most pressing concerns—labor shortages, budget overruns, and misalignment between stakeholders—require strategic solutions. Sessions will cover:
With three full days of interactive audience breakouts, speed networking, and expert panels, ADCC West is the perfect setting to connect with top professionals from the data center construction ecosystem.
📅 Tuesday, March 18, 2025 | ⏰ 10:30 AM
🎤 Panel: Setting Projects Up for Success
Doxel joins top industry leaders in a discussion on reducing change orders, managing scope, and ensuring seamless project execution.
ADCC West provides exclusive insights, actionable takeaways, and the opportunity to connect with key decision-makers in data center construction. Doxel’s panel will help you:
✔ Reduce project risks by aligning execution with client expectations.
✔ Improve collaboration with AI-driven project tracking.
✔ Gain real-world strategies for minimizing scope changes and delays.
📍 Join us in Salt Lake City to learn how Doxel is transforming data center construction.
🔗 Learn more about the event here

This collaboration marks a significant step forward in Lean Construction, merging Doxel’s cutting-edge progress tracking technology with Touchplan’s proven production planning capabilities to enable an optimized construction workflow that bridges the gap between planning and execution.
SAN FRANCISCO, CA & BOSTON, MA – January 14, 2025 – Doxel, an industry leader in AI-driven construction progress tracking, and MOCA Systems, Inc. (MSI), the provider of the leading production planning platform, Touchplan, are excited to announce a new partnership. This collaboration marks a significant step forward in Lean Construction, merging Doxel’s cutting-edge progress tracking technology with Touchplan’s proven production planning capabilities to enable an optimized construction workflow that bridges the gap between planning and execution.
With construction project costs rising and schedules shrinking, forward-thinking owners and contractors alike look to advanced technologies to help ensure on-time, on-budget project completion. But they struggle to effectively integrate diverse, individual technologies into their project workflows.
Doxel and Touchplan working together offer a powerful solution that helps construction teams achieve project deadlines with greater predictability, efficiency, and profitability. The Touchplan Lean planning platform enables easy, accurate sequencing and scheduling of all construction workflow tasks, enhancing trade coordination and eliminating waste on the jobsite, while Doxel’s progress tracking solutions provide real-time feedback on actual project progress.
"If teams use Touchplan alongside Doxel, it will provide excellent confirmation that what we have done is what we said we were going to do,” said Adam Nelson, Project Controls Manager at CRB. “It also allows us to look forward in the progress charts and ensure our forecasts for activities align."
"Strong planning meets strong execution when Touchplan and Doxel are used together,” said Saurabh Ladha, CEO and Founder of Doxel. “This collaboration embodies Lean Construction values, creating a dynamic real-time feedback loop between planning and on-site execution. Construction teams can stay nimble, informed, and aligned every step of the way.”
“Customers using Doxel’s AI progress tracking and Touchplan’s planning platform gain a powerful advantage in Lean Construction. Touchplan’s planning capabilities, combined with Doxel’s visual tracking and predictive analytics, help teams proactively manage workflows and stay on track, reducing rework and costly errors. For contractors and owners, the combined use of Touchplan and Doxel enhances transparency, project predictability, and the quality of the final deliverable,” said Brett Adamczyk, President, MSI Software.
The partnership between MSI and Doxel marks a transformative step in the tech-laggard construction industry, bringing a new ability to bridge the historic gap between planning and execution. By combining Touchplan’s digital Lean planning with Doxel’s AI-driven progress tracking, project teams gain the clarity, visibility, and real-time insights needed to achieve exceptional results and ensure project success.
For more information, visit website.
###
Media Contact:
Julie Blackley
Marketing Communications Manager
MOCA Systems, Inc.
press@mocasystems.com
Exploring Trends Around Building at Scale, Designing for Artificial Intelligence, and Supporting Energy Infrastructure
Exploring Trends Around Building at Scale, Designing for Artificial Intelligence, and Supporting Energy Infrastructure
DATE: FEB. 20. 2025 @ 9:00 AM EST / Virginia
FEATURED SESSION: 2:45 PM – 3:30 PM EST
Redefining the Status Quo: Best Tools, Approaches, and Techniques to Build the Most Efficient and Innovative Data Centers
With AI and its power demands at the forefront of stakeholders' minds, examining how to push the boundaries of standard design and practices and reduce inefficiencies will be critical to the bottom line. How are developers and their partners working to reduce the carbon footprint and rethink standard practices as more data centers with larger footprints come online?






Moderator

Join industry leaders to explore the evolving trends and challenges shaping data center construction and design in East Coast markets. Learn how developers and stakeholders are navigating critical topics, including:
Connect with decision-makers in commercial real estate, including owners, investors, engineers, designers, and industry executives.
Stay ahead of industry trends, uncover opportunities, and strengthen your network in a rapidly growing sector.
For speaking or sponsorship inquiries, contact Adam Knobloch at adam.knobloch@bisnow.com.
"The Future of Smart Hospitals and Healthcare Industry" event is Oracle's premier gathering for owners, healthcare stakeholders, and technology innovators.
📅 Date: February 4, 2025
📍 Location: Oracle Industry Lab, Deerfield, IL.
"The Future of Smart Hospitals and Healthcare Industry" event is Oracle's premier gathering for owners, healthcare stakeholders, and technology innovators. Hosted at the renowned Oracle Innovation Center, this venue provides a dynamic space for showcasing cutting-edge solutions in healthcare construction. Known for hosting unique events like reality capture demonstrations and indoor drone races, the Innovation Center sets the stage for forward-thinking collaboration.
This year, Oracle emphasizes owner attendance and healthcare-focused content, making it a prime opportunity to engage with key decision-makers shaping the industry's future.
Doxel will participate in Oracle's interactive Hands-on Innovation Experiences, delivering 15-minute sessions demonstrating how our technology revolutionizes project tracking and execution for healthcare construction projects.
With a focus on owners and healthcare decision-makers, this event provides unparalleled access to industry leaders.
It's an excellent opportunity to foster strong relationships with Oracle's product team and other innovators in the healthcare construction space.
Through the Hands-on Innovation Experience, we'll highlight how Doxel's capabilities drive better outcomes and more innovative processes for healthcare construction.
We're excited to be part of this visionary event and look forward to sharing highlights and insights from "The Future of Smart Hospitals and Healthcare Industry." One of our top product leaders will represent Doxel at the event, ensuring insightful engagement with attendees and Oracle's team.
Learn more about the event here.
Understand how every system contributes to trade-level progress with clearer visibility into on-site activities.
In the fast-paced construction of data center, life sciences, manufacturing, and hospital projects, keeping up with construction progress is both challenging and essential. Increasing project complexity requires greater emphasis to coordinate work and understand risk on the project.
That’s why we’re excited to introduce Systems View within Doxel’s Work In Place (WIP) view. This new capability offers a deeper, system-level visualized breakdown of construction progress, giving teams clearer visibility into on-site activities and enabling a more precise understanding of the project's status.
Systems View is an advanced feature in the WIP view that allows teams to go beyond trade-level tracking, providing a detailed 3D view of construction progress for specific systems within each trade, such as hot water and chilled water within plumbing. Systems view is particularly useful for complex mechanical, electrical, and plumbing systems. This added layer of granularity offers project teams deeper insights into the progress of each system, empowering them to monitor and manage intricate project details.
In complex projects, traditional tracking did provide valuable trade-level insights but often lacked the detail needed to align each system with Takt times, leading to inefficiencies. With Systems View, project teams will gain real-time, system-specific insights that empower them to monitor each system’s adherence to Takt schedules, catching issues before they become bottlenecks.
With this added visibility, teams can identify delays early and reallocate resources as needed to maintain steady progress. Ultimately, Systems View reinforces Takt Planning and the Last Planner System, driving projects toward efficient milestone completion.
Imagine a typical Monday coordination meeting for a data center project. The Project Manager or Supervisor is focused on the progress of the mechanical system in Data Hall 1, where multiple subcontractors are working concurrently. The meeting kicks off with questions about the status of supply ducts and whether the HVAC team has completed their work.
With Doxel's Systems View, the project engineer can instantly access progress data for HVAC ducts, filtering by both system and zone. In just moments, the team discovers that only 80% of the supports are installed, with delays caused by mechanical piping in the same area. Using the system filter, they isolate the data and confirm that the piping crew is scheduled to finish by day’s end, clearing the path for the HVAC team to complete their work.
This level of real-time, system-specific insight enables more effective coordination, allowing the supervisor or project manager to make informed decisions on the spot. The result? No wasted time, better workflow sequencing, and a more streamlined project timeline.
Data center construction is highly sophisticated, involving multiple systems that must be meticulously coordinated. Before the introduction of Systems View, project managers relied on trade-level data, making it challenging to understand system-specific delays or progress. With Systems View, project managers can:
For example, in one data center project, the HVAC system installation was delayed due to incomplete electrical work in the same zone. Using Systems View, the project engineer quickly identified the bottleneck, reallocated resources, and adjusted schedules. This proactive management helped the team finish the system installation on time, preventing downstream delays and additional costs.
Industries like life sciences, manufacturing, and healthcare demand strict timelines, compliance, Strict timelines, compliance requirements, and intricate system interdependencies drive construction projects in industries like life sciences, battery manufacturing, and hospitals. Systems View empowers project managers to:
Systems View helps teams deliver complex facilities efficiently and predictably, whether managing cleanroom infrastructure, advanced manufacturing lines, or hospital surgical suites. By providing granular tracking, it enables earlier inspections, faster system sign-offs, and mitigates risks that could impact schedules or budgets.
Stay tuned as we continue to enhance Doxel's capabilities, bringing more tools to help you deliver projects on time and within budget.
Construction projects have long struggled with inefficiencies, fragmented workflows, and unmet expectations from technology. Using Doxel and Touchplan together offers a unified workflow for continuous improvement. Together, these platforms empower teams to reduce waste, enhance collaboration, and achieve outstanding project results.

"If teams use Touchplan alongside Doxel, it would provide excellent confirmation that what we have done is what we said we were going to do. It would also allow us to look forward in the progress charts and ensure our forecasts for activities align." said Project Controls Manager, CRB.
Transform your weekly planning from a manual, time-intensive process into a dynamic, digital workflow. Touchplan’s digital pull planning and Look-Ahead Planning tools enable real-time collaboration, helping teams anticipate roadblocks and ensure efficient planning at every project phase.
Doxel uses AI-driven progress tracking to provide live updates on project execution. By automating activity monitoring and delivering visualized progress insights, Doxel keeps site performance aligned with plans, ensuring accountability and maximizing productivity.
Touchplan and Doxel combine advanced technology with proven Lean Construction methods to create a unified workflow for continuous improvement. Teams can analyze progress trends, address inefficiencies, and refine workflows, driving success both today and on future projects.
Leaders like CRB are already experiencing measurable success, setting a new benchmark for construction excellence
Doxel is excited to partner with DCAC, the people’s conference designed to inspire and evolve the data center industry.
Doxel is excited to announce its participation in the groundbreaking Data Centre Automation Conference (DCAC) Live Europe 2024 conference, which will be held in Dublin, Ireland, from October 15 to 16, 2024.
Doxel is excited to partner with DCAC, the people’s conference designed to inspire and evolve the data center industry. Aligned with DCAC’s mission to disrupt, challenge, and foster collaboration, Doxel looks forward to contributing to the meaningful conversations and connections that propel visionaries, builders, and manufacturers forward in this fast-growing sector.
DCAC Live Europe 2024 will gather top industry professionals from the world of data center automation and focus on how cutting-edge technology can enhance critical infrastructure efficiency, scalability, and automation.
Doxel accelerates construction by automating progress reporting, identifying hidden issues early, preventing rework, and improving collaboration through visual data. Attendees will be able to see advanced Doxel features, including:
Doxel’s platform automatically leverages AI to track project progress, providing real-time insights into productivity, cost, and quality. This allows teams to make data-driven decisions, reducing delays and keeping projects on budget.
Doxel uses predictive analytics to spot potential risks before they turn into problems. This proactive approach helps teams avoid costly overruns and delays in projects, keeping them running smoothly and on time.
With Doxel, data is collected automatically throughout the project lifecycle. This allows for continuous progress monitoring and ensures stakeholders have visibility into every aspect of the construction process.
Doxel’s simple dashboards make complex data easy to understand and help teams make quick, informed decisions for better project results.
Visit Doxel’s table for live demonstrations of its AI-driven platform. See how automated progress tracking helps monitor, manage, and control every stage of your data center project. Meet with the Doxel team to discuss challenges and explore custom solutions tailored to your needs.
As the demand for data centers grows, effective and automated construction progress tracking is more critical than ever. DCAC Live Europe 2024 is a great opportunity for data center professionals to learn about the latest in automation and technology. With expert-led discussions, technical workshops, and solution showcases, attendees will stay ahead in the evolving data center landscape.
DCAC Live Europe:
Website: DCAC Live Europe 2024

Insights from DCAC 2024 with Doxel CEO Saurabh Ladha and Joseph Pinzon, CRO of Overwatch.
In the latest episode of the Data Center Revolution Podcast from DCAC 2024, Saurabh Ladha, CEO of Doxel and Joseph Pinzon, CRO of Overwatch deliver an insightful conversation on the cutting-edge advancements in data center construction. Here are some of the topics covered during the podcast:
Catch the full conversation below and explore how technology is reshaping data center construction:
– Joseph Pinzon, CFO, Overwatch.