Identify and recover Production Delays
A Project Manager used Doxel production rates to predict a critical path pipe insulation activity was to finish 3 weeks late, even though manual reporting onsite estimated it was on track. The field then used Doxel’s data to justify doubling the crew size, helping to recover in time and avoid a lengthy delay.