Identify and Recover Production Delays

A project manager used Doxel’s production rate tracking to identify that a critical-path equipment installation was running three weeks behind schedule—despite manual reports suggesting it was on track. By leveraging Doxel’s production rate tracking, the field team justified doubling the crew size, recovering lost time, and preventing costly delays in plant commissioning.