Identifying and Recovering Delays

A hospital construction project manager used Doxel’s production rate tracking to detect that a critical-path pipe insulation activity was trending three weeks behind schedule—despite manual reports indicating it was on track. By leveraging Doxel’s production rate reporting, the team justified doubling the crew size, recovering lost time, and preventing a costly project delay that could have impacted hospital operations.